Sol 75 – LT Ramp on Rosy Red, EEProm update (uplinked Saturday night, downlink Sunday 8/10)

Sol 76 – HT Day 1 on Rosy Red. Uplink Sunday night, downlink Monday afternoon – report on results Tuesday 8/12/08 am.

Sol 77 – HT Day 2 & Checkout, Uplink Monday - Downlink Tuesday late afternoon 8/12, report on results Wednesday 8/13/08 am.

Sol 78 – Pump, Uplink Tuesday night 8/12, Downlink Weds night 8/13, report on Thursday 8/14 am.

Sol 80 – Pump ), Uplink Thursday night, Downlink Friday afternoon 8/15, report on Saturday 8/16 am.

Note: This may get shifted to Sol 81 if Strategic Systems does not have time to review all of the test results. Library update was not ready – validation still inprocess.

Sol 81 – Library update was pulled due to validation delays. Move to Sol 82. Down day for TEGA, uplink Friday – RAC image of TA7 door open. RA will acquire the sample. Library update will go in the PM pass for Sol 81.

Sol 83 – Sample Acquire/LT Ramp, TA 7 Burned Alive, uplink Sunday night, downlink late afternoon Monday, report on Tuesday 8/19/08 am.

Sol 84 – MT uplink Monday night, downlink late afternoon Tuesday report on Wednesday 8/20/08 am.

Sol 86 – HT Day 2, Checkout uplink Weds night, downlink late afternoon Thurs, report on Friday 8/22 am.

Sol 87 – TEGA Pump uplink Thurs night, downlink late afternoon Friday, report on Friday 8/23/08 am.